We the Subcontractor had encountered a Contractor risk which caused a Delay to our programme which is Accepted. We raised a Compensation event within the time scales allowed as this impacted a Completion Date
4 months have passed, and we await response to that NCE which the Contractor has requested time to review. Around 2 months after raising the NCE above, we the Subcontractor have caused a delay to the Contractor which impacts the Completion date above.
The Contractor is now claiming that because our delay is the prominent delay, I.e stops us completing the Sectional Completion Date, we are not entitled to cost or time and liable to LD’s
My question is, should delays be assessed in the sequence they occur, ignoring any knowledge of delays we the Subcontractor we’re not aware at the time of raising the NCE (Dividing Date). I understand that the Accepted Programme should be used at the point of the Dividing Date, and at that time, this was not an issue or known to be an issue.
It appears the Contractor has intentionally prolonged their response to pass the responsibility for the delay.to the Subcontractor. .