After giving a notice of adjudication, how long does a Party have to provide a copy of the information and supporting documents he has provided to the Adjudicator to the other Party?
After giving a notice of adjudication, a Party provides a copy of the information and supporting documents he has provided to the Adjudicator to the other Party within seven days (see Clause W2.3(2)).