NEC ECC: Recovery of labour costs for Option A/C/E due to COVID-19
|
|
1
|
496
|
28 April 2020
|
NEC ECC: Option A (Contractor Design) and updating Contractor's Works Information
|
|
1
|
958
|
23 April 2020
|
NEC ECC: Can Project Manager change their mind that something is a CE?
|
|
2
|
1497
|
23 April 2020
|
NEC ECC: We have been asked to provide a CE quotation under the NEC 3 but will take 1 day of site measure to cost accurately. How best am I to recover this cost?
|
|
2
|
507
|
21 April 2020
|
NEC ECC: non acceptance of quotation submitted under Clause 61.2
|
|
1
|
477
|
21 April 2020
|
NEC ECC: What costs are recoverable if Client stops work due to funding issues?
|
|
1
|
356
|
16 April 2020
|
NEC ECC: a CE Weather Event - is it calendar days or working days?
|
|
1
|
1434
|
16 April 2020
|
NEC ECC: Option B and changing rates?
|
|
1
|
777
|
15 April 2020
|
NEC ECC: Lack of access - is this a time-bar(able) compensation event?
|
|
1
|
559
|
15 April 2020
|
NEC ECC: Applying People Overhead Fee to Sub-Contractors within a compensation event quotation
|
|
1
|
866
|
13 April 2020
|
NEC ECC: Option B - pricing compensation event for similar work
|
|
1
|
529
|
13 April 2020
|
NEC ECC: What is the methodology that the Contractor goes through to assess the cost included in a quotation? (NEC 4 Option B)
|
|
1
|
1502
|
7 April 2020
|
NEC ECC: Impact of a compensation event
|
|
1
|
1085
|
7 April 2020
|
COVID-19 notifications
|
|
1
|
706
|
6 April 2020
|
NEC ECC: Suspension Under 34.1 during Coronavirus period
|
|
4
|
732
|
3 April 2020
|
NEC ECC: Novated designer changes the design - is this a compensation event?
|
|
1
|
765
|
3 April 2020
|
NEC ECC: Notifying COVID-19 as a compensation event
|
|
1
|
771
|
3 April 2020
|
NEC ECC: COVID - work stop - Employer query - CE assessment
|
|
1
|
612
|
1 April 2020
|
NEC ECC: Option B, change to WI. Can we claim cancellation costs incurred?
|
|
1
|
338
|
1 April 2020
|
NEC ECS: Option A - Change in quantities
|
|
4
|
2044
|
1 April 2020
|
NEC ECC: Challenge of a Z Clause relating to Corona Virus
|
|
6
|
788
|
31 March 2020
|
NEC ECC: How many events (60.1(1) to (21)) can you put in a notification ?
|
|
5
|
1258
|
31 March 2020
|
NEC PSC: Option C - What information is required with a quotation?
|
|
1
|
672
|
27 March 2020
|
NEC ECS: Coronavirus - Compensation Event Options
|
|
2
|
724
|
27 March 2020
|
NEC ECC: Compensation Event Retrospective Claim
|
|
2
|
950
|
27 March 2020
|
NEC ECC: Which CE Clause to use due to Coronavirus?
|
|
1
|
543
|
26 March 2020
|
NEC ECC: Is the lack of an NCE crucial for an Access Date Change in Adjudication?
|
|
2
|
502
|
25 March 2020
|
NEC Contracts: Force Majeure - Corona Virus?
|
|
3
|
1890
|
25 March 2020
|
NEC ECC: Project Manager acceptance of implemented CE under clause 65.1
|
|
1
|
1235
|
23 March 2020
|
NEC ECC: Compensation Event for Physical Conditions following Corona virus
|
|
1
|
641
|
23 March 2020
|