NEC3 ECC Option A: No response to NCE raised
|
|
2
|
945
|
6 August 2020
|
NEC ECC: Is it a Compensation Event for PM instruction issued under NEC3 Clause 17.1?
|
|
4
|
788
|
27 July 2020
|
NEC ECC: Compensation Event or Contractor's Proposal
|
|
1
|
957
|
27 July 2020
|
NEC ECC: Does a Negative CE include the fee % as a negative or Positive value
|
|
1
|
1580
|
27 July 2020
|
NEC ECS: Information relating to the Quotation
|
|
1
|
546
|
24 July 2020
|
NEC ECS - additional works for Subcontractor
|
|
1
|
506
|
22 July 2020
|
NEC ECC: Can works be removed from a Contractors scope without warning?
|
|
1
|
659
|
22 July 2020
|
NEC ECC: Time impact assessment of CEs
|
|
3
|
2767
|
14 July 2020
|
NEC ECC: Assessment of quotation under 61.2 request for quotation
|
|
1
|
513
|
10 July 2020
|
NEC ECC: Is the purchase of Contractor safety equipment in relation to COVID 19 a Compensation Event under a Nec4 ECC Option C contract?
|
|
4
|
657
|
10 July 2020
|
NEC4 ECC B: Are travel to site costs Defined Cost?
|
|
2
|
1552
|
8 July 2020
|
NEC ECSS: Scope items not priced in the activity schedule/BoQ
|
|
2
|
611
|
8 July 2020
|
NEC3 PSC Option E - Inclusion of Fee Percentage on Expenses
|
|
1
|
730
|
8 July 2020
|
NEC ECC: When should the CE have been instructed?
|
|
2
|
744
|
8 July 2020
|
NEC3 ECC Option A - Unistructed works carried out by the Contractor
|
|
4
|
573
|
6 July 2020
|
NEC ECS: Rejection of the Compensation Event Due to Critical Path Change
|
|
1
|
563
|
6 July 2020
|
NEC ECC: Retained Plant Damage Risk Allocation
|
|
1
|
488
|
4 July 2020
|
NEC ECSC: Is a change in Law a CE under the NEC3 Short Contract?
|
|
1
|
558
|
4 July 2020
|
NEC ECC: NEC4 ECC Option C design and build: COVID-19 as a Compensation Event
|
|
1
|
524
|
4 July 2020
|
NEC ECC: Option B should we programme the Scope or the B of Q?
|
|
3
|
1107
|
3 July 2020
|
NEC ECS: Under NEC3 ECS, can a Contractor communicate change to a Subcontractor on a response to a Technical Query?
|
|
1
|
479
|
2 July 2020
|
NEC ECC: Notification of a Compensation Event - when is it accepted?
|
|
1
|
527
|
2 July 2020
|
NEC4 - Covid - Main Option C - Are we entitled to deduct the Government wage subsidy from the value of the Compensation Event and the payment claim
|
|
1
|
536
|
1 July 2020
|
NEC ECC: Amending a rate in BOQ due to inconsistency between BOQ and Works Information
|
|
3
|
709
|
1 July 2020
|
NEC ECC: Contractor has installed a lower performance item this was accepted by the PM
|
|
1
|
482
|
30 June 2020
|
NEC ECC: Implementing the impact programme before the costs of CE
|
|
1
|
676
|
29 June 2020
|
PSC NEC3 Option C - Programme delay compensation event
|
|
4
|
883
|
29 June 2020
|
NEC ECSC: Clause 62.3 CE quote acceptance
|
|
1
|
733
|
28 June 2020
|
NEC3 ECC Option B: What costs can a Contractor reasonably claim for when access to site is not possible due to Others
|
|
1
|
460
|
25 June 2020
|
NEC ECC: Item in Scope but not in BofQ for an option B contract
|
|
2
|
1703
|
24 June 2020
|