Why would the Project Manager want to give an early warning?
1 Like
Firstly, because he is obliged to under Clause 16.1 and not to do so would be a breach of contract. Secondly, giving an early warning increases the time available to consider the problem with the Contractor; improving the chances of finding a solution to the problem.