When does the period that the Project Manager has to notify the Contractor of his assessment of an even begin?
This period starts when the need for the Project Manager’s assessment becomes apparent (see Clause 64.3).
When does the period that the Project Manager has to notify the Contractor of his assessment of an even begin?
This period starts when the need for the Project Manager’s assessment becomes apparent (see Clause 64.3).