What types of damages should the Employer make pre-estimates for in the Contract Data?
Appropriate entries for delay damages may comprise amounts for:
Loss of rent,
Loss of profit from a manufacturing facility,
Costs due to a delayed start of another contract,
Interest on the capital invested in the project for the period during which the Employer has been deprived of its benefit.