What types of damages should the Employer make pre-estimates for in the Contract Data?

What types of damages should the Employer make pre-estimates for in the Contract Data?

Appropriate entries for delay damages may comprise amounts for:

	Loss of rent,

	Loss of profit from a manufacturing facility,

	Costs due to a delayed start of another contract,

	Interest on the capital invested in the project for the period during which the Employer has been deprived of its benefit.