48 days of awarding the contract, the same as a Part A.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
Procurement: With regard to procurement legislation, when do the minimum timescales associated with a contract begin? | 1 | 427 | 22 February 2013 | |
With regards to procurement legislation, what are the timescales associated with the negotiated procedure? | 1 | 428 | 22 February 2013 | |
What are the minimum timescales from PIN to contract award? | 1 | 454 | 13 February 2013 | |
If a Buyer Profile is used for downloading tender documents can contracting authorities use a shorter timescale for receipt of tenders? | 1 | 423 | 13 February 2013 | |
With regards to procurement legislation, what are the timescales associated with the open procedure? | 1 | 440 | 22 February 2013 |