What is Disallowed Cost?
Disallowed Cost is cost which the Project Manager decides:
Is not justified by the Contractor’s accounts and records,
Should not have been paid to a Subcontractor in accordance with his contract,
Was incurred only because the Contractor did not: give an early warning; or follow an acceptance or procurement procedure stated in the Works Information (see Clause 11.2(25)).