Does the Contractor pay the excess if the Price for Work Done is greater than the Total of the Prices?
Yes. If the Price for Work Done is greater than the Total of the Prices, the Contractor pays his share of the excess (see Clause 53.9).
Does the Contractor pay the excess if the Price for Work Done is greater than the Total of the Prices?
Yes. If the Price for Work Done is greater than the Total of the Prices, the Contractor pays his share of the excess (see Clause 53.9).