What does the Project Manager do on receiving notification of an early warning from the Contractor?
NEC3 and NEC4 Contracts
General
BuiltIntelligence
12 October 2012 16:31
2
The Project Manager enters the early warning matter in the Risk Register (see Clause 16.1).
show post in topic
Related topics
Topic
Replies
Views
Activity
How does the Project Manager or the Contractor notify of an early warning?
General
2
1080
16 November 2021
The Project Manager has become aware of a matter which could delay Completion. What should he do?
General
1
510
12 October 2012
The Project Manager has become aware of a matter which could impair the performance of the works in use. What should he do?
General
1
613
12 October 2012
Why would the Project Manager want to give an early warning?
General
1
735
12 October 2012
The Project Manager has become aware of a matter which could delay meeting a Key Date. What should he do?
General
1
559
12 October 2012