The Project Manager has become aware of a matter which could delay Completion. What should he do?

The Project Manager has become aware of a matter which could delay Completion. What should he do?

1 Like

The Project Manager must give an early warning by notifying the Contractor and entering the matter in the Risk Register (see Clause 16.1).