What action should an adjudicator take if a jurisdictional point is raised during an adjudication?
Legal and Disputes
Adjudication
Legal_Expert
18 January 2013 09:42
2
The adjudicator should decide whether to continue with the adjudication or to resign.
Related topics
Topic
Replies
Views
Activity
When may the enforcement of an adjudicator's decision be rejected by a court or an arbitrator?
Adjudication
1
486
18 January 2013
If either party wishes to make a jurisdictional point in adjudication, when should this be raised?
Adjudication
1
478
18 January 2013
When a surveyor is representing a client, whether making or defending a claim, what is one of the first issues to consider in adjudication?
Adjudication
1
506
18 January 2013
What should the Parties do if the Adjudicator resigns?
NEC3 and NEC4 Contracts
1
637
15 October 2012
Once jurisdiction has been confirmed, what is the next issue is to confirm in adjudication?
Adjudication
1
451
18 January 2013