Under Option W2, a dispute arising in connection with the contract referred is referred to whom?
A dispute arising under or in connection with this contract is referred to and decided by the Adjudicator (see Clause W2.1(1)).
Under Option W2, a dispute arising in connection with the contract referred is referred to whom?
A dispute arising under or in connection with this contract is referred to and decided by the Adjudicator (see Clause W2.1(1)).