There has been a dispute about a matter not mentioned in the Adjudication table. Which Party may refer the dispute to the Adjudicator?

There has been a dispute about a matter which is not specifically mentioned in the Adjudication table. Which Party may refer the dispute to the Adjudicator?

If there is a dispute about a matter not specifically mentioned in the Adjudication table, either Party may refer it to the Adjudicator (see Adjudication table W1.3).