The Contractor has terminated because the Employer is an individual and has made an arrangement with his creditors (R4). What is the termination procedure?
1 Like
The Parties follow the procedures outlined in P1 and P4 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and the Contractor leaves the Working Areas and removes the Equipment.