ReachBack
Programme (NEC)
NEC3 and NEC4 Contracts
Paulodi7
7 September 2023 18:14
1
Should the programme record PMIs (and should it only be once they are agreed)?
Thanks
Related Topics
Topic
Replies
Views
Activity
Programme Data Date, As-built, PMI
NEC3 and NEC4 Contracts
1
431
27 August 2021
NEC ECC: Deemed Programme Acceptance
NEC3 and NEC4 Contracts
3
3112
3 November 2017
NEC3 Contract Programme - Half the scope
NEC3 and NEC4 Contracts
1
349
6 June 2019
NEC3 ECC: Cl 32.1 - Changes to the Accepted Programme
Time
1
1338
13 January 2016
NEC 4, Option A - The accepted programme
NEC3 and NEC4 Contracts
5
866
22 September 2021