BI Toolkit
BI Toolkit
ReachBack
Programme (NEC)
NEC3 and NEC4 Contracts
Paulodi7
7 September 2023 18:14
1
Should the programme record PMIs (and should it only be once they are agreed)?
Thanks
Related topics
Topic
Replies
Views
Activity
NEC3 ECC: Cl 32.1 - Changes to the Accepted Programme
Time
1
1410
13 January 2016
Webinar - How to produce and update your programme under NEC3 ECS
NEC3 and NEC4 Contracts
5
464
14 September 2023
NEC3 Contract Programme - Half the scope
NEC3 and NEC4 Contracts
1
389
6 June 2019
NEC ECC: Clause 32.2 submitting programme on PM instruction
Time
2
1648
10 October 2019
Can the PD be instructed to use your (PC) programme dates by the client?
NEC3 and NEC4 Contracts
0
30
24 March 2025