ReachBack
Once a building has been completed, how many days does the occupier / owner have to inform the local authorities of the energy rating of the building?
Planning and Architecture
Part A Structure
Build_Regs_Advisors
7 February 2013 13:02
2
The requisite period for this is five days.
Related Topics
Topic
Replies
Views
Activity
Does my work with asbestos insulating board (AIB) need a licence or is it notifiable non-licensed work?
Asbestos
1
43018
14 January 2013
When is an asbestos licence required?
Asbestos
1
680
14 January 2013
What is the procedure should a building site contain possible contaminants?
Part D Toxic substances
1
472
14 February 2013
As a client, do I have to provide information about asbestos that may be present in the structure?
CDM
1
447
24 January 2013
As a client, do I have to provide information about asbestos that may be present in the structure?
CDM
1
455
24 January 2013