BI Toolkit
BI Toolkit
ReachBack
Once a building has been completed, how many days does the occupier / owner have to inform the local authorities of the energy rating of the building?
Planning and Architecture
Part A Structure
Build_Regs_Advisors
7 February 2013 13:02
2
The requisite period for this is five days.
Related topics
Topic
Replies
Views
Activity
Before commencing with a legal order to demolish a building, how much notice does the person(s) involved have to give the local authorities?
Part A Structure
1
370
14 February 2013
When a local authority is contacted regarding the demolition of a building, what period do they have in which to respond?
Part A Structure
1
422
14 February 2013
Once a building notice has been issued, for what period does it remain valid?
General
1
386
7 February 2013
When applying to a local authority to have the right to demolish a dangerous building or structure, to whom should this notice be submitted?
Part A Structure
1
355
7 February 2013
What two conditions have to be satisfied before building work commences?
General
1
405
7 February 2013