ReachBack
Once a building has been completed, how many days does the occupier / owner have to inform the local authorities of the energy rating of the building?
Planning and Architecture
Part A Structure
Build_Regs_Advisors
7 February 2013 13:02
2
The requisite period for this is five days.
Related topics
Topic
Replies
Views
Activity
Before commencing with a legal order to demolish a building, how much notice does the person(s) involved have to give the local authorities?
Part A Structure
1
361
14 February 2013
When a local authority is contacted regarding the demolition of a building, what period do they have in which to respond?
Part A Structure
1
421
14 February 2013
With regard to Building Regulations, if a local authority serves an abatement order to the owner / occupier of building, does the owner / occupier have any recourse?
Part A Structure
1
343
7 February 2013
If an individual wishes to engage in building work related to foundations, excavations for foundations, any damp-proof course, any concrete or other material to be laid over a site and drains or sewers, how many days’ notice needs to be given to the loca
Part C Site prep
1
424
7 February 2013
What two conditions have to be satisfied before building work commences?
General
1
402
7 February 2013