NEC4- Option C Contract.
The Contractor has submitted a quotation for a compensation event notified under 60.1 by the Project Manager giving an instruction to change the scope.
CE Quotation is received which details a week long cost for ‘prolongation of works’ and allocated costs however no delay is claimed to key dates or completion.(62.2).
Is it correct that a week long prolongation to works is claimed where no time delay is claimed or is shown on the approved programe?