The Contractor has submitted a quotation for a Compensation Event. The quotation has been accepted and implemented by the PM.
The implemented quotation has subsequently been discovered to contain an arithmetical error which if corrected, would increase the value of the quotation.
Is the PM obliged to rectify the Contractors arithmetical error and if so, how should this be done?