The accepted programme shows a duration for a third party task based on the knowledge and experience of the contractor, if this task duration needs to be extended at the request of the third party is the contractor entitled to a compensation event?
1 Like
Under 60.1(5) the answer should be yes. This clause provides that where an Other does not work within the times shown on the Accepted Programme then the Contractor is entitled to a compensation event.