NEC3 ECC certifying completion of sections of works

The PM is required to certify Completion under cl. 30.2 and our ECC contract includes X5. Cl. X5.1 states “unless stated otherwise… each reference… to Completion…applies, as the case may be, to either the whole of the works or any section of the works.” Does this wording require the PM to certify Completion of each section fo the works under cl. 30.2?

In brief, ‘Yes’ for each section of works.

Also remember that the Supervisor should be identifying a list of any Defects and that the defect correction period kicks in.