This is for a PSC NEC3 contract. The consultant is on a framework with agreed framework rates.
Consultant appointed in 2016 for a package of projects. There are been numerous CE’s that have pushed the completion date for the projects out. Now that most of these projects are complete or near completion, the consultant is putting in a Compensation event for increased rates, as the deliverableS now are effectively costing more than originally planned due to previous compensation events. i.e a document tender to be complete in 2017 being completed in 2019 has a higher cost associated with it.
Are they entitled to put this in, after the event has happened?
If the contractor thought they would be entitled to this, should this not have been included in each compensation event that pushed the programme completion date out, as each compensation event should be for the impact to the programme by that compensation event?
No Z22 clause in the contract. Hope this makes sense.