What is the consequence/risk if the Contractor decides the date of Completion (for a subcontractor) but does not certify Completion within one week of this date as they are required to do under clause 30.2?
For example; If the Contractor decided that the date of Completion was 1st April for a subcontractor but failed/forgot to certify Completion within one week. He then certifies Completion on 28th April but still states that the date of Completion is 1st April?