NEC ECC: Restarting works

Can the Contractor request the works to be restarted after receiving a Project Manager instructions to stop the works?

1 Like

As the Contractor I suggest you could notify an early warning to state that if the works are not restarted soon it would be a potential issue? That should prompt a meeting, a discussion and the Project Manager to record an action in the Risk Register (or Early Warning Register under NEC4).