I’ve started working on a project that is nearly complete but has a number of small CEs occurring. The contract is NEC3 ECC Option A, and when it was priced the Contractors were also asked to price a BoQ as well as an activity schedule (that was given to them to price).
I’m assessing a quotation from the contractor and our PM wants to use rates from the BoQ as he says they are applicable to most of the work in the quote.
What is the correct process here, as I’ve never seen a BoQ used alongside an activity schedule?