The contract is NEC3 Option A,
The Project Manager has issued an instruction to omit a 250mm diameter duct run and 4 chambers, shown on the drawings but is not detailed/specified in any other document;
Can the Project Manager assess this as an omission to the Total of The Prices.
The drawings are annexed to the Employers Work Specification which forms part of the Works Information.
The duct run is not detailed within the Employers Work Specification or any other document forming part of the Works Information.
All other duct runs are specifically identified on both the drawings and within the Employers Work Specification under the Scope of Works section.