NEC ECC: In step 3 (of assocaited question), where is progress taken up to; to the CE notification date?

Yes - under NEC4 where they have given it a name which is “the dividing date” you take into account progress up until the “dividing date”. This is the date the instruction was given (if the instruction results in a compensation event) or for all other events when the compensation event was notified.

Basically anything that you know has changed before the dividing date can be assessed (but would have to be proven/justified).