My PM is looking for me to claim prelim costs for a 3 day delay that has had no effect on the programme. I have submitted for the costs of the operatives who were delayed but I don’t believe I can claim for an extension of prelim costs if programme shows completion has not moved?
2 Likes
I assume you mean your own internal Contractors “PM”. Yes you are correct. If there is no effect on planned Completion there is no entitlement to price “prelim” type costs or to move Completion date as a result of this CE.
Any CE it is always only the impact on planned completion that will result in Completion Date moving out.