What is the entitlement to time on concurrent CE’s which occur on the critical path and affect Completion?
For example say there is a delay to an activity which, when shown on the clause 60 programme (produced from the accepted 32 at the time), gives an extension of two weeks. And say that at the same time a separate activity is instructed which, when shown on the clause 60 against the same clause 32 as the previous delay, overtakes the critical path and results in a change to planned Completion again of two weeks.
The total effect on the Contractors planned Completion is two weeks but the entitlement to movement in the Completion date appears to be four weeks, two weeks for each CE. This is due to the Completion date on the accepted programme not being updated until submission of the next clause 32 and it would appear that the Contractor has benefited from the overlap in the events and gained two weeks terminal float.