Is the due date (following IVD) counted as week days or calendar days and if calendar days what happens if the due date falls on a weekend?
You need to check your Sub-Contract Particulars but assuming they follow the standard JCT approach the Interim Valuation Date is a fixed date in each month and if that date falls on a weekend or public holiday, is the nearest Business Day in that month.