Is either Party obliged to accept the other’s proposal to change the Works Information and accept a Defect?

Is either Party obliged to accept the other’s proposal to change the Works Information and accept a Defect?

1 Like

No. Neither Party is obliged to accept the other’s proposal to change the Works Information and accept a Defect.