This is dependent upon whether or not the contractor wishes to claim loss and /or expense or damages by using any of the standard form contracts. Should a contractor wish to do so, then it has a duty to mitigate its loss.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
When an architect is charged extra fess for work which results from a contractor breaching certain obligations, can the employer recover these fees from the contractor? | 1 | 443 | 5 February 2013 | |
In the event that work is omitted, is a contractor entitled to loss of profit? | 1 | 1335 | 5 February 2013 | |
Contractor Claim for Increased Costs under Loss and Expense | 1 | 558 | 25 April 2022 | |
What is the procedure if a contractor wishes to claim for disruption? | 1 | 530 | 5 February 2013 | |
If a construction contract calls for fittings from a foreign county, is it legally permissible for a contractor to claim additional fees due to detrimental exchange rates? | 1 | 419 | 5 February 2013 |