BI Toolkit
BI Toolkit
ReachBack
In a construction contract, is it permitted for a project manager to change the date of possession?
JCT Contracts
JCT_Experts
4 February 2013 14:33
2
In short, no. The only people permitted to alter the contract are the employer and the contractor.
Related topics
Topic
Replies
Views
Activity
In a construction contract, if an employer is unable to award possession by the due date can this be overcome by the architect instructing for the Works to be postponed?
JCT Contracts
1
611
4 February 2013
Can the Project Manager change a Key Date?
General
1
676
12 October 2012
Can any other parties change the Works Information?
General
1
596
12 October 2012
Can a client put back the date for practical completion?
JCT Contracts
1
1485
9 January 2014
NEC3 ECC: changes to the Contract Data - what is in the power of the Project Manager to instruct?
General
4
8059
13 October 2019