BI Toolkit
BI Toolkit
ReachBack
In a construction contract, is it permitted for a project manager to change the date of possession?
JCT Contracts
JCT_Experts
4 February 2013 14:33
2
In short, no. The only people permitted to alter the contract are the employer and the contractor.
Related topics
Topic
Replies
Views
Activity
In a construction contract, if an employer is unable to award possession by the due date can this be overcome by the architect instructing for the Works to be postponed?
JCT Contracts
1
604
4 February 2013
Can the Project Manager change a Key Date?
General
1
670
12 October 2012
Can any other parties change the Works Information?
General
1
596
12 October 2012
In an JCT Standard Building Contract 2009 contract, can an employer rearrange sections of the contract without instruction from an architect?
JCT Contracts
1
575
5 February 2013
Can a client put back the date for practical completion?
JCT Contracts
1
1470
9 January 2014