In a construction contract, is it permitted for a project manager to change the date of possession?
JCT Contracts
JCT_Experts
4 February 2013 14:33
2
In short, no. The only people permitted to alter the contract are the employer and the contractor.
Related topics
Topic
Replies
Views
Activity
Can a client put back the date for practical completion?
JCT Contracts
1
1437
9 January 2014
In an JCT Standard Building Contract 2009 contract, can an employer rearrange sections of the contract without instruction from an architect?
JCT Contracts
1
574
5 February 2013
When undertaking an JCT Standard Building Contract 2009 contract, an architect approves a contractor's programme, with the completion date indicated post-dating the contract completion date by two months. Should the architect work towards the new date?
JCT Contracts
1
359
4 February 2013
Can the Project Manager change a Key Date?
General
1
666
12 October 2012
Once an architect has improved a contractor's programme, is it possible for a contractor to alter it without informing the architect, and does the architect have the legal right to demand an update?
JCT Contracts
1
418
4 February 2013