If there is a change in the law, are the Prices reduced?
If the effect of a compensation event which is a change in the law is to reduce the total Defined Cost, the Prices are reduced (see Clause X2.1).
If there is a change in the law, are the Prices reduced?
If the effect of a compensation event which is a change in the law is to reduce the total Defined Cost, the Prices are reduced (see Clause X2.1).