If the Employer uses a part of the works before Completion has been certified, is he then responsible for providing access?
1 Like
If the Employer uses a part of the works before Completion has been certified, he is then responsible for providing access so that the Contractor can correct Defects, which will include completing outstanding work (see Clause 43.4).