How long does the Adjudicator have to decide a dispute?

How long does the Adjudicator have to decide a dispute?

The Adjudicator decides the dispute and notifies the Parties and the Project Manager of his decision and his reasons within four weeks of the end of the period for receiving information (see Clause W1.3(8)).