How long after the Adjudicator has made his decision can a Party refer a dispute to the tribunal?
A Party can only refer a dispute to the tribunal within four weeks of the Adjudicator’s decision (see Clause W1.2(2)).
How long after the Adjudicator has made his decision can a Party refer a dispute to the tribunal?
A Party can only refer a dispute to the tribunal within four weeks of the Adjudicator’s decision (see Clause W1.2(2)).