How is the liability of a Party to indemnify the other reduced if events at the other Party’s risk contributed to the claims, proceedings, compensation and costs?
1 Like
The liability of a Party to indemnify the other is reduced according to how far events at the other Party’s risk contributed to the risk event (see Clause 83.2).