From what point is the Contractor paid a bonus for early Completion?

From what point is the Contractor paid a bonus for early Completion?

The Contractor is paid a bonus each day from Completion or the date on which the Employer takes over the works (whichever date is earlier) until the Completion Date (see Clause X6.1).