ReachBack
ECC Option A contract - Sub - Contractors
NEC3 and NEC4 Contracts
General
fastdraft
,
nec
Leasedline
27 August 2021 05:48
4
Hey I’m new here. we are
Best leased Line Providers
in UK. i must say that its really amazing forum.
show post in topic
Related topics
Topic
Replies
Views
Activity
Why might the Project Manager not accept the Contractor’s proposed appointment of a Subcontractor?
General
1
618
12 October 2012
Under an NEC3 ECC contract does a contractor need the Employers / Project Managers consent to change subcontract terms?
General
2
2536
9 December 2014
NEC ECC: What is the procedure for dealing with proposed subcontractors?
General
1
621
13 February 2020
NEC Contract ECC Option C - Subcontractor acceptance
General
1
1461
9 July 2014
NEC ECC: What if a Subcontractor or their terms are NOT issued for acceptance - what is the risk to the Contractor?
General
1
448
9 September 2019