ReachBack
ECC Option A contract - Sub - Contractors
NEC3 and NEC4 Contracts
General
nec
,
fastdraft
Leasedline
27 August 2021 05:48
4
Hey I’m new here. we are
Best leased Line Providers
in UK. i must say that its really amazing forum.
show post in topic
Related topics
Topic
Replies
Views
Activity
Why might the Project Manager not accept the Contractor’s proposed appointment of a Subcontractor?
General
1
609
12 October 2012
Under an NEC3 ECC contract does a contractor need the Employers / Project Managers consent to change subcontract terms?
General
2
2507
9 December 2014
NEC ECC: What is the procedure for dealing with proposed subcontractors?
General
1
547
13 February 2020
NEC Contract ECC Option C - Subcontractor acceptance
General
1
1455
9 July 2014
NEC ECC: What if a Subcontractor or their terms are NOT issued for acceptance - what is the risk to the Contractor?
General
1
442
9 September 2019