Does Completion of a section of the works affect the defects date?
No. Completion of a section of the works does not affect the defects date, which is defined by reference to Completion of the whole of the works.
Does Completion of a section of the works affect the defects date?
No. Completion of a section of the works does not affect the defects date, which is defined by reference to Completion of the whole of the works.