Do projects with a domestic client, and which last longer than 30 days, or 500 person days of construction work, require a CDM co-ordinator, a principal contractor, a written construction phase plan and a health and safety file?

No. This is because a domestic client is not a ‘client’ as defined by the Regulations, and Part 3 of the Regulations does not apply to projects where there is a domestic client.