Yes. Where the project is notifiable, designers should not start work (other than initial design work) unless a CDM co-ordinator has been appointed. They must also provide the CDM co-ordinator with any information about aspects of their design which will help them discharge their CDM 2007 duties, including information that may be needed for the health and safety file