Dividing Date for Impossible requirement

When an impossible requirement is notified under Clause 17.2 is the dividing date the date of notification or the date when an instruction is issued by the Project Manager under Clause 14.3 amending the Scope to remove the impossible requirement.

1 Like

The notification of an illegal or impossible requirement is a different notification to that of a compensation event. Consequently, it will from when the PM issues an instruction changing the Scope (if that is where the illegal or impossible requirement is stated).