Can the Supervisor, Project Manager or Employer inform the Contractor of Defects after the defects date?

Can the Supervisor, Project Manager or Employer inform the Contractor of Defects after the defects date?

2 Likes

Yes, but the Contractor may not be liable for them - depending on the cut-off period for the Contractor’s responsibility for latent defects or the liability date in Clause X18.5 if Option X18 is used.