Can rates and lump sums be used to assess a compensation event instead of Defined Cost?

Can rates and lump sums be used to assess a compensation event instead of Defined Cost?

If the Project Manager and the Contractor agree, rates and lump sums may be used to assess a compensation event instead of Defined Cost (see Clause 63.14).