At whose risk is adverse weather that has occurred more frequently than once in ten years?
Adverse weather which does not meet the tests in Clause 60.1(13) is at the Contractor’s risk in relation to both cost and time.
At whose risk is adverse weather that has occurred more frequently than once in ten years?
Adverse weather which does not meet the tests in Clause 60.1(13) is at the Contractor’s risk in relation to both cost and time.