At whose risk are Claims, proceedings, compensation and costs payable which are due to negligence, breach of statutory duty or interference with any legal right by the Employer or by any person employed or contracted to him except the Contractor?
1 Like
The event is at the Employer’s risk (see Clause 80.1).