Leroy,
Here are a few points to consider.
I presume the EWN was not time barred.
Did the Contractor reply to your EWN? Or did the Contractor fail to reply and thus create a CE under 60.1(6).
Was there a Risk Reduction Meeting derived from the EWN?
Was the Risk Register amended after the RRM?
You issued a Compensation Event Notification relating to 60.1(1), relating to a Contractor’s Instruction (not a PMI, as you don’t have a contractual relationship with the Project Manager).
Did the Contractor reply to your CEN? Or did the Contractor fail to reply and thus create a CE under 60.1(6).
Was the Contractor’s Instruction issued in accordance with the Subcontract?
Were you invited, by the Contractor, to submit a Quotation for the CE, or did you submit an unsolicited quotation, due to the Contractor not acting “as stated in this subcontract” – in breach of clause 10.1?
Did the Contractor detail under what contractual authority they requested “the elements of the quote”?
You refer to a PMI, but I presume that you mean a Contractor’s Instruction regarding the Quotation. Is this a different instruction from the one mentioned above, which generated the EWM?
I don’t know the details, but it seems that the Contractor’s qualified acceptance of your quotation isn’t an acceptance at all. Moreover it seems to be a flagrant breach of clause 10.1. See recent Scottish appeal Court case of Van Oord v Dragados.
I’d be happy to get involved, or give you more guidance if you want to contact me directly.
Neil - note that this issue is on a NEC3 subcontract, so there is no clause 10.2, it’s all in 10.1.